Monday, November 14, 2011
Latest at Goodland and Ashley
GOODLAND, KS.
All 3 tank slabs have been completed. Next is tank wall assembly |
ASHLEY, MI.
Tuesday, November 8, 2011
Williams, IA Facility to Expand Spring 2012
Beginning spring 2012 the Williams, IA facility also will be expanding with 3- 500,000 ga tanks along with installation of a rail spur, truck load-out building and scales.
Aerials depict the present look at the Williams facility
Concept drawing illustrates the intened expansions to occur. Highlighted borders show current operations in brown and blue for the upcoming new development.
Aerials depict the present look at the Williams facility
Concept drawing illustrates the intened expansions to occur. Highlighted borders show current operations in brown and blue for the upcoming new development.
First foundation floor complete
Yesterday the foundation slab was completed on the first tank
Plan is for the second tank to be completed today however the looming forecast is for 5-10" inches of snow.
Thursday, November 3, 2011
New project begins in Ashley
This week work began at the Ashley site preparing for 3- 500,000 gallon tanks to be installed spring 2012. Trench was dug that runs to the 3 tanks for the muliple lines to supply fertilizer, electric , air and water hydrant.
LIQUID's Ron Andrews and Randy Harris work at installing the electrical service to each tank. Also able to see sections of 4" stainless lines welded and placed. Once all welds are complete a pressure test will take place checking for leaks.
Also in this project a rail manifold will be constructed. The pads seen running along the spur will support the piping, in all the trunk line will span 600 feet reaching 10 cars.
Crew from Two Guy's Mechanical are preforming the welding fabrication. Excavating by Miller and Son's.
Wednesday, November 2, 2011
Goodland Tank(ing) Shape
Progress continued yesterday, here the outer ring for the foundation is completed
A self leveling slurry is poured prior to foundation floor
Rebar is laid and outer wall formed ready for cement.