Monday, June 11, 2012

FEW SITE UPDATES

BEFORE


 It’s been awhile since we’ve checked in on the Ashley Facility, the most recent action was the last touches put on at the rail area, there was a section dividing the containment and first spur that yet needed the concrete slab poured. By doing this it keeps the mud and muck off the equipment, is a much improved area for the workers along with the visual enhancement as seen in a reference picture from this past fall.
AFTER


This past week at Goodland it was busy pumping concrete just as well as fertilizers. Brent’s Concrete finished concrete along the containment pad adjacent to the new half million gallons tank, adding this Goodland facility now has the ability in combination to load / unload 4 truck simultaneously along with utilizing railcars

 
Footing have been poured for a hoop structure that will soon cover one of the outside loading pads, this was needed due to the high winds and bluster of sand that that comes with those winds. This feature will alleviate the hazardous to the worker atop of the vessel along with attention to product quality.   
These couple pictures are update to the demo and reconstruction of the dock to the south side of the building, once complete this will be fully enclose eliminating any need the dock work to be exposed to the elements, Its know ACLF continues to do the best to make working conditions as convenient as necessary, but a little exposure  to rain and snow would be all that bad.


Wednesday, June 6, 2012

THE DAY HAS ARRIVED

The first soil has been broken in creation for the new Global Headquarters as we wonder if the day would every come, it has arrived.
As with all good managed projects there’s a gathering of the minds as seen.
Now that the minds have gathered a plan can be set forth for the work to begin. Here the first cuts are being made peeling off the top soil to expose the clay, needless to say this didn’t take many passes to reveal that cantankerous material.
In the distance passes are made cutting in what will eventually be the secondary entrance leading up to the office.
This square and leveled area will become what’s considered the lay-down area for placement of project trailers and staging of equipment
No this mini hoe is not attempting to become stuck it is stripping back the vegetation preparing lay in the culvert for the construction drive for the duration of the project.
Another view looking at what will serve as the construction drive, this will be well used for the numerous amounts of soils to remove and be replaced.

Friday, June 1, 2012

Stockton, CA. First Site Staff on Duty

Shauns latest travels to the new Stockton location first on the docket was to fill the postions of night duty security, please welcome Heathcliff  and the newest LIQUID employee.
Also on his trip Shawn meet with the new insurance agent, though they'd like their company name to remain anonymous, he went by the name Martin

GETTING to the ODDS and ENDS at GOODLAND


Past few weeks some of the behind the scene side projects have been taking place. The truck dock that has served us for many years was just not cutting it so what the solution,  cut it out and start over and make it better and more cozy by protecting the lift drivers from the elements.


  When complete there will be installation of a new air operated dock lever along with weather gasket sealing up between the trailers and building to create an air tight seal.


The latest onsite improvement to commence is a 100’ long canopy covering the length of the outdoor loading bay. The intent for this is to protect from the wicked sand storms of the might west of Goodland. If you have experienced any of them you can relate and if you haven’t you are glad you don’t understand what the big deal is.



Friday, May 11, 2012

GLOBAL HEADQUARTERS

Can you see it? Look harder for all the little markers, okay its only survey stakes now but still pretty exciting.
Over the next 15 months will provide many more meaningful pictures as we watch together a crop of wheat transitions to the new Global Headquarters......   

Tuesday, May 1, 2012

PUTTING THE FINAL TOUCHES ON GOODLAND

Robert was kind enough to take time out of another hectic day to send along few updated pictures.  
This sequence of photos shows the completion of the rail manifold along with a series of transfer lines being finalized 

  Thanks to Two Guys Mechanical for their creative assembly consistent to the model facility ACLF is always motivated towards

Wednesday, April 25, 2012

Along with the numerous upgrades to the daily operations at the Goodland Facility cannot forget the little things too. The main office got a new entry canopy reflecting the updated logo, pretty sharp!

Next few photos show the troughed dug beneath the rail spur to incase the steel flume that will allow running of the many fluid transfer lines.  

Many pad containments have been strategically positioned to control minor spills or those nuisance drips. The pad contouring the spur will house the load / unload rail manifold.

This week Two Guys Mechanical are on site again fabricating the many pipes and joints for the fluid transferring . Also on-site for the past week are Ron Andrews and Randy Harris from our Michigan location, they are working to continue hooking up the numerous components that run all the automations upgrades along with sonar sensor to monitor the liquid levels for the 500,000 ga tanks. Weather permitting and God willing both crews will be closing in on their last trips.