Thursday, September 30, 2010

Ashley 9/30/10

They poured warehouse and ramp area today.  All major excavation within building is complete.  Employee parking area will be poured tomorrow, raceways within building finished next week, building cement continued following week.  Things are moving very fast now.

 Henry from Custom Concrete discussing the grade changes to the employee parking area.

 Parking area all formed and ready to go with curb modifications.
 Interior Building Trenching Complete.
 Office Footing excavation
 Raceway Excavation
Power Dock plate cement work complete ready for installation of docks.
 80 feet of Warehouse cement and truck loading/unloading ramp complete.  207 yards of cement today.
Remainder of Warehouse cement - Running out of light - have to go.