Randy Harris works to finish up a channel cut out in the concrete that will allow connecting of product transfer lines between each containment. Newly constructed office to service loading and unloading tank cars and trucks
Installation of upgraded loading system with 4" meter, 6" pump & 6" filterContainment pads were poured recently for transfer pumps at the 500,000 gallons tanks
Fabricated flume to be installed beneath the rail spur that will house 12- 4" lines for product transfer