Wednesday, April 25, 2012

Along with the numerous upgrades to the daily operations at the Goodland Facility cannot forget the little things too. The main office got a new entry canopy reflecting the updated logo, pretty sharp!

Next few photos show the troughed dug beneath the rail spur to incase the steel flume that will allow running of the many fluid transfer lines.  

Many pad containments have been strategically positioned to control minor spills or those nuisance drips. The pad contouring the spur will house the load / unload rail manifold.

This week Two Guys Mechanical are on site again fabricating the many pipes and joints for the fluid transferring . Also on-site for the past week are Ron Andrews and Randy Harris from our Michigan location, they are working to continue hooking up the numerous components that run all the automations upgrades along with sonar sensor to monitor the liquid levels for the 500,000 ga tanks. Weather permitting and God willing both crews will be closing in on their last trips.




Tuesday, April 17, 2012

GROUNDBREAKING FOR NEW GLOBAL HEADQUARTERS

Wed April 11 a ceremony was held to commence groundbreaking on the new global headquarters for Agro Culture LIQUD Fertilizers.
Troy Bancroft (President and CEO) and Nick Bancroft (VP of Operations) address the gathering of 85 attendees consisting of media, community and employees.



Representatives from sectors of the project join in for the inaugural shovel toss



Right around the corner earth moving equipment is expected to be arriving on location to begin what will certainly be exciting progress to following over the next 12-13 months