Pumping north of Containment.
Finishing Loading Pad
Thursday, October 28, 2010
Wednesday, October 27, 2010
Ashley 10/27/10
Plant & Loadout area nearly ready for cement
Office area plumbing rough in - Chasco says that there will be 2 miles of tubing for the floor heat in the office and storage area.
Warehouse Cement
Truck Loadout pad ready to pour in the morning.
Office area plumbing rough in - Chasco says that there will be 2 miles of tubing for the floor heat in the office and storage area.
Warehouse Cement
Truck Loadout pad ready to pour in the morning.
Thursday, October 21, 2010
Ashley 10/21/10
It was a wet week causing probably not as much progress as was hoped for. This area was prepped for the truck unloading pad.
Much work was done stabilizing the area west of the containment.
Temporary power is nearly complete for the meter to be used in the new building
More warehouse cement was poured last Thursday. Looks like a big warehouse.
Underground raceways are being installed. There are several pictures here showing the process. It is quite time consuming.
Office area has been brought up to grade.
Gas service is installed on building. Waterline can also be seen (black stand pipe).
Much work was done stabilizing the area west of the containment.
Temporary power is nearly complete for the meter to be used in the new building
More warehouse cement was poured last Thursday. Looks like a big warehouse.
Underground raceways are being installed. There are several pictures here showing the process. It is quite time consuming.
Office area has been brought up to grade.
Gas service is installed on building. Waterline can also be seen (black stand pipe).
Williams 10/20/10
I had the chance to visit Williams this week, looking for opportunities to upgrade the existing containment. It was good to see everyone there and see as always, how smoothly things run. There was very little distribution equipment on site, meaning that the wheels are turning getting product delivered.
Wednesday, October 13, 2010
Ashley Update 10/13/10
Much Underground work in progress. We took the SR MGT up there after our meeting this week to see progress.
Rail Loadout office near completePreparing to pour warehouse floor.
Many of the pits for the underground raceways have been installed
Finished grade is 8 inches below top of pits.
Consumers was in to install gas lines.
Friday, October 8, 2010
Ashley Update 10/8/10
Much Happening again this week.
Beginning to install the West DrivewayTower base is in and done correctly the first time.
Office & Storage Area Footings
Raceway Pit Footings
Plant wall and Raceway Walls
Jib Crane Footing and Elevator Pit
Inside Elevator Pit
Glen working on all the details
Power Trenched West of the containment
Rail Loadout Office - Go Green!
Rail Loadout Office - Go White!
Inside Rail Loadout Office. Ready for final Electrical.
Sunday, October 3, 2010