Much Underground work in progress. We took the SR MGT up there after our meeting this week to see progress.
Rail Loadout office near completePreparing to pour warehouse floor.
Many of the pits for the underground raceways have been installed
Finished grade is 8 inches below top of pits.
Consumers was in to install gas lines.