Thursday, June 2, 2011

Ashley 6/2/11

Still lots to work on up to Ashley.  Truck inside loadout and New Rail install and beginning of Directional Boring.
 Rail looking south.
 Rail looking North.  The switch is installed for the second line.
 Manifolds, pumps and meters installed for the truck loadout.
 You can see the Endruss Hauser meter to the left (Half circle pipe) and the Micro Motion meter in the background (Box).  Both of these meters will pump at the same time to deliver product mixes in record time.
 This is one of the loadout arms for overhead loading of trucks.  You can see it positioned over the trailer.

Directional Boring machine is anchored and ready to bore a drainage hole all the way under the building over to the railroad.  They can "steer or guide" the drill within inches left right and up down.
You can see here how the line will be bored.  This will take care of any water problems in the building and the rail area.