Tuesday, August 16, 2011

Ashley - Open House Preparations

We are getting ready for the open house at an rapid pace.  Things are coming together nicely with the excavation finishing up.  Everybody is getting everything spruced up and getting the final things put together and cleaned up.

 Below is the NE corner of the site that was used as a staging area for all of the materials.
 New cement is finished North of the building leaving lots of good parking spots.

 The railroad was doing some repairs on the main line.
 They were doing final grading between the truck parking and the railroad.  This will be where the 3 - 500,000 gal tanks will go.
 The train went by when we were there - that always makes a good picture.  The cones in the gravel are marking the center line of the new tanks.
 New spur is complete.  There is still some material to add to level things up but everything is final graded.  Looks much nicer than the tree swamp that was there before.
 The city is working on finishing up the water main project along Sectionline St. I hope they get that done and cleaned up by the show.
 You can see the lighted directional sign.  Everything is coming along good.  Looking forward to the public open house August 24th from 4-6:30 - Everyone is welcome so tell all your friends.