Monday, June 11, 2012

FEW SITE UPDATES

BEFORE


 It’s been awhile since we’ve checked in on the Ashley Facility, the most recent action was the last touches put on at the rail area, there was a section dividing the containment and first spur that yet needed the concrete slab poured. By doing this it keeps the mud and muck off the equipment, is a much improved area for the workers along with the visual enhancement as seen in a reference picture from this past fall.
AFTER


This past week at Goodland it was busy pumping concrete just as well as fertilizers. Brent’s Concrete finished concrete along the containment pad adjacent to the new half million gallons tank, adding this Goodland facility now has the ability in combination to load / unload 4 truck simultaneously along with utilizing railcars

 
Footing have been poured for a hoop structure that will soon cover one of the outside loading pads, this was needed due to the high winds and bluster of sand that that comes with those winds. This feature will alleviate the hazardous to the worker atop of the vessel along with attention to product quality.   
These couple pictures are update to the demo and reconstruction of the dock to the south side of the building, once complete this will be fully enclose eliminating any need the dock work to be exposed to the elements, Its know ACLF continues to do the best to make working conditions as convenient as necessary, but a little exposure  to rain and snow would be all that bad.


No comments:

Post a Comment