Monday, November 14, 2011

Latest at Goodland and Ashley

GOODLAND, KS.  
All 3 tank slabs have been completed. Next is tank wall assembly
completion for this segment is 24-26 days                    
 
ASHLEY, MI.

Rail manifold is near complete. Two Guys Mechanical will be back on Tuesday to finishing up the fabrication. Once that is done the last few items of connections within the containment and electrical out to the pump will be made.

 

  