Friday, September 14, 2012

UPDATES TO THE ONGOING LIQUID PROJECTS

Williams, IA facility continues to make progress with the installation of the 500,000 ga. storage tanks. The machine in here is a automated seam welder that completed all the horizontal welds, all vertical weld still are done with human automation.



Excavation continues to proceed for the structure that will contain 1,650,000 gallons of 30,000 ga. tanks. The footprint of the complete containment will be 192’L x70’W x3.5’D.

The first ½ million ga. tank is closer to completion soon moving on to the begin construction of the second tank. With the latest exciting growth updates from the sales force, ownership this week gave the thumbs up to sign off to immediately install a 3rd tanks as well.


CORPORATE HEADQUARTERS: Following sequence of picture displays progress over the past few weeks.
 
 
 
 
 
 

 

No comments:

Post a Comment