In this photo, the crew is finishing up the concrete in the south side load bay.
The north load bay is prepped and ready to be poured. Under all the re-rod is a 6' wide x 4' deep tunnel which will be used for routing rubber hose around the site. The extra strength is needed in the floor to support the heavy truck loads.
The finish product. This week, the truck load out platform will be assembled followed by the office that sits on top of the platform. A crew from AK Equipment in Michigan is heading out to CA this week to set trusses and pull the roof fabric. They have a long drive but we anticipate the roof will be finished in a couple weeks.