Wednesday, February 29, 2012

ON SITE AT GOODLAND

Last Week Shaun Schneider and I (Tony) took a road trip to Goodland, KS site to see for ourselves the progress on the 500,000 ga tank project.


View of the tanks from back of site near the rail yard  

To remain in compliance for complete containment these valve structures were installed 

Dust Bowl?
Beefed up with new 800 amp service to comply with all the upgrades

Wednesday, February 15, 2012

Another Milestone for Agro Culture Liquid Fertilizers

February 14, 2012 marked another milestone for Agro Culture Liquid Fertilizers. Official announcement was delivered to immediately begin construction on a new 42,402 sq ft Corp Headquarters to be located adjacent to the current office. The announcement was giving by Troy Bancroft (CEO) during a meeting attended by owners, employees, local land owners and the selected partnering firms for the project venture of Wieland-Davco Corp., Hobbs + Black Architects and LSG engineers.  These displayed renderings are conceptual at this time but represent what the final completion will portray.      








Wednesday, February 8, 2012

More Than Just Tanks at Goodland

Another project in process at Goodland is an upgraded exterior load-out office. This newly constructed office is 16'x16' replacing the previous smaller 8'x12'.
 Beside larger and cozier there will be operational upgrades also for loading trucks and tank cars.
Touch screen monitors will be implemented and supported by an PLC system to advance accuracy.
On the efficiency side 25HP 6"x4" pumps will be installed, doing so will increase the Gallons Per Minute (GPM) from 250 to an expected 600 GPM or higher.   

Thursday, February 2, 2012

GROWING WEST

As the  company continues to grow and expand so must the project list to stay pace with the future at the world of LIQUID. The latest checked off from the project list was purchasing property in Stockton, California
 The property is 13 acres, to begin the site will serve as a stocking point with phased development.

Phase 1 to begin immediately will include construction of 60'x100' two bay truck loading building along with a 50'x100' containment for 540,000 gallons of storage using 18- 30,000 gallon tanks.


Along with the purchase of the property the site included this 2,100 sq ft office and rail spur to accommodate 7 tank cars

Projected operational date of Phase 1 is June-July 2012