Another project in process at Goodland is an upgraded exterior load-out office. This newly constructed office is 16'x16' replacing the previous smaller 8'x12'.
 Beside larger and cozier there will be operational upgrades also for loading trucks and tank cars.
Touch screen monitors will be implemented and supported by an PLC system to advance accuracy.
On the efficiency side 25HP 6"x4" pumps will be installed, doing so will increase the Gallons Per Minute (GPM) from 250 to an expected 600 GPM or higher.   