Last Week Shaun Schneider and I (Tony) took a road trip to Goodland, KS site to see for ourselves the progress on the 500,000 ga tank project.


View of the tanks from back of site near the rail yard  

To remain in compliance for complete containment these valve structures were installed 

Dust Bowl?
Beefed up with new 800 amp service to comply with all the upgrades