The property is 13 acres, to begin the site will serve as a stocking point with phased development.
Phase 1 to begin immediately will include construction of 60'x100' two bay truck loading building along with a 50'x100' containment for 540,000 gallons of storage using 18- 30,000 gallon tanks.
Along with the purchase of the property the site included this 2,100 sq ft office and rail spur to accommodate 7 tank cars
Projected operational date of Phase 1 is June-July 2012